Project Description:
CF Group were appointed to manage the site and Design & Install CSM shoring wall, capping beam, bracing for temporary support. Scope of Works also included Full bulk excavation, detail excavation, dewatering, lift pit shoring.
Scope of Work :
  • CSM Retaining Wall – 104Lin.m for 2 Basements
  • Capping Beam – 104Lin.m (650mmx600mm)
  • Temporary Steel Bracing – 6No – CHS610
  • Bulk and Detailed Excavation
  • Dewatering
  • Sheet Piling
  • Turn Key
Equipment Used:
Bauer RTG19