North Styne and Whistler Street, Manly

Client : Made Property Group

Address: 89 - 90 North Styne & 90 - 92 Whistler St, Manly, NSW 2025

Scope of Work

Project Description:
Cutter soil mix shoring wall. Sheet pile wall for lift pit, 1 row of temporary ground anchors & steel bracing, bulk& detailed excavation and dewatering.
Scope of Work :
  • TSM (Tripple Soil Mix) – 137Lin.m for 2 Basements
  • TSM Barrettes – 14Lin.m
  • Capping Beam – 137Lin.m (600mmx600mm)
  • Temporary Steel Bracing – 6No – CHS406
  • Bulk and Detailed Excavation
  • Dewatering
  • Sheet Piling
  • Turn Key
Equipment Used:
Bauer RTG19

Share:

Recent Projects

Send Us A Message