Scope of Work

Project Description:
  • Demolition of Existing Structure
  • D&C of CFA foundation piles
  • Piling Platform Installation
  • Site Remediation
Scope of Work :
  • Demolition of Existing Structure
  • Installation of CFA Foundation Piles
  • Design and Installation of Piling Platform
  • Remediation and Removal of soil and piling spoil
Equipment Used:
  • 2No. Liebherr LB36 piling rigs (CFA)
  • 2No. Liebherr THS110 D5 Concrete Line Pump
  • 28t and 48t Dump Truck
  • Various Size Excavators ranging from 2.5t to 50tonne
  • Hyundai Loader