Skip to content
02 9316 4012
info@cfgroup.net.au
Euston Rd, Alexandria NSW 2015
Facebook-f
Instagram
Linkedin-in
Home
Capabilities
Shoring Walls
Foundation Piles
Ground Anchors and Internal Bracing
Turnkey Packages – Piling and Earthworks
Equipment
Projects
About
About us
Safety First
Our Team
Careers
Contact
Menu
Home
Capabilities
Shoring Walls
Foundation Piles
Ground Anchors and Internal Bracing
Turnkey Packages – Piling and Earthworks
Equipment
Projects
About
About us
Safety First
Our Team
Careers
Contact
Data Centre, Huntingwood
Client :
AW Edwards
Address:
24 Healey Circuit, Huntingwood
Scope of Work
Project Description:
Demolition of Existing Structure
D&C of CFA foundation piles
Piling Platform Installation
Site Remediation
Scope of Work :
Demolition of Existing Structure
Installation of CFA Foundation Piles
Design and Installation of Piling Platform
Remediation and Removal of soil and piling spoil
Equipment Used:
2No. Liebherr LB36 piling rigs (CFA)
2No. Liebherr THS110 D5 Concrete Line Pump
28t and 48t Dump Truck
Various Size Excavators ranging from 2.5t to 50tonne
Hyundai Loader
Share:
Recent Projects
Alexandria Foundation Piles
Broadbeach
Iconica Surfers Paradise
Jacques Av. Bondi
Send Us A Message
Full Name
Phone
Email
Message
Upload File ( max file size upto 10mb only)
Send
Prev
Previous
Rockdale Central
Next
Surry Hills Shopping Village
Next